RSA provided mechanical and electrical engineering design services for the 28,885 SF replacement K–12 school and associated modular prime power plant in Mertarvik. The campus was designed as a fully self-sustaining facility in a remote Arctic environment, integrating heating, power generation, fire protection, and life-safety systems into a coordinated infrastructure.
Design services were delivered through full construction documents 21-0552, including prime power generation and waste heat recovery integration 22-0146.
Featured Mechanical Systems
- Boiler plant in adjacent utility building
- Generator waste heat recovery to heating system
- Arctic piping between generator and boiler plant
- Arctic-rated generator module ventilation
- Interior fuel oil day tank and piping
- Electric fire pump with on-site fire water storage
- Heat recovery ventilation units
- Performance-specified building controls
Featured Electrical Systems
- Stand-alone diesel prime power plant
- Multi-generator configuration
- Generator paralleling and transfer switches
- Dedicated transfer switch for fire pump
- Switchgear and campus distribution
- Voice evacuation fire alarm system
- Telecom, IP video, wireless clocks, AV systems